How to install the ground bridge?

2026/01/16 10:40

The installation of ground cable trays can be carried out according to the following steps:

1. Prepare the necessary materials and tools, including cable trays, connectors, wrenches, cutting tools, etc.

2. As needed, use cutting tools to cut the bridge frame to the desired length and shape.  

3. Place the bridge in the desired position and secure it to the ground using connectors.  

4.For cable trays that require suspension, lifting ropes or rings can be used for suspension.  

5. For cable trays that need to be connected, connectors can be used to ensure a secure and reliable connection.  

6.For cable trays that require the installation of support frames, installation should be carried out according to design requirements to ensure the stability and reliability of the support frames.  

7. Finally, perform surface treatment on the bridge to meet the required appearance requirements.  

During the installation process, the following points should be noted:

1. Ensure that the size and weight of the bridge meet the requirements and avoid using unqualified products.  

2.During the installation process, attention should be paid to safety to avoid accidents such as personal injury or equipment damage.  

3. During installation, relevant electrical safety regulations should be followed to ensure that the electrical performance of the bridge meets the requirements.  

4. During installation, relevant building decoration specifications should be followed to ensure that the appearance of the bridge meets the requirements.